Douglas County legal - 26857

 BEFORE THE PUBLIC UTILITIES COMMISSION OF NEVADA 

NOTICE OF JOINT APPLICATION AND 

NOTICE OF PREHEARING CONFERENCE 

On August 1, 2022, Nevada Power Company d/b/a NV Energy (“NPC”) and Sierra Pacific Power Company d/b/a NV Energy (“SPPC” and collectively with NPC, “NV Energy”) filed with the Public Utilities Commission of Nevada (“Commission”) a joint application (“Joint Application”), designated as Docket No. 22-08001, for approval of the second amendment to their 2020 Joint Natural Disaster Protection Plan (“NDPP”). 

The Joint Application requests the Commission: 1) Accept the Amendments to the NDPP as it is set forth in Exhibit B to the Joint Application; 2) Approve the 2022 NDPP Underground Prioritization Plan set forth in Exhibit C to the Joint Application; 3) Approve the 2022 NDPP Tree Attachment Plan set forth in Exhibit D to the Joint Application; 4) Approve the increase of $25,048,473 for Operation Maintenance and General Administration (“OMAG”) within the NDPP; 5) Approve an increase of $17,191,692 in capital funding for SPPC; 6) Approve NV Energy’s request to allow the 2022 forecasted budget to be carried-over to 2023; 7) Approve NV Energy’s request to reallocate the budgeted amounts between programs; 8) Approve NV Energy’s request to defer $5,802,458 in NPC underground budget to the next triennial plan; and 9) Grant such additional other relief as the Commission may deem appropriate and necessary. 

This Notice serves only to notify the public that the Commission has received the above-referenced filing. It is the responsibility of interested persons to review the filing and monitor the proceedings to determine their desired levels of involvement based on how this matter may affect their unique situations. The details provided within this Notice are for informational purposes only and are not meant to be an all-inclusive overview of the filing. The Commission may consider and adopt alternative proposals not contained within the filing, but which are related to the subject matter of the filing and supported by substantial evidence. 

NV Energy filed the Joint Application pursuant to the Nevada Revised Statutes (“NRS”) and the Nevada Administrative Code (“NAC”), Chapters 703 and 704, including, but not limited to, NRS 704.7983 and Section 8(2) of the NDPP Regulations adopted in Docket No. 19-06009, LCB File No. R085-19.

Interested and affected persons may file petitions for leave to intervene pursuant to NAC 703.578 through 703.600 electronically through the Electronic Filing System on the Commission’s website or at either of the Commission’s offices on or before WEDNESDAY, AUGUST 31, 2022. 

A person who wishes to participate as a commenter may file written comments pursuant to NAC 703.491. A commenter is not a party of record and shall not take any action that only a party of record may take. Pursuant to NAC 703.500, only parties of record are entitled to enter an appearance, introduce relevant evidence, examine, and cross-examine witnesses, make arguments, make and argue motions and generally participate in the proceeding. 

NOTICE IS HEREBY GIVEN that, pursuant to NAC 703.655, the Commission has scheduled a PREHEARING CONFERENCE in this docket to be held as follows: 

THURSDAY, SEPTEMBER 8, 2022 

10:00 a.m. 

Hearing Room A 

Public Utilities Commission of Nevada 

1150 East William Street 

Carson City, Nevada 89701 

VIA VIDEOCONFERENCE TO 

_____________________________________ 

The Commission adopted regulations in accordance with SB 329 in Docket No. 19-06009, which were filed with the Secretary of State in LCB File No. R085-19 on February 27, 2020. 

Hearing Room A 

Public Utilities Commission of Nevada 

9075 West Diablo Drive, Suite 250 

Las Vegas, Nevada 89148 

And VIA MICROSOFT TEAMS 

The parties will appear and otherwise participate in the continued prehearing conference either in person or remotely via Microsoft Teams. The parties should provide the email address, title/ role in associated business or organization, and business address for each person who intends to participate via Microsoft Teams to Commission Hearing Officer Samuel S. Crano at scrano@ puc.nv.gov no later than FRIDAY, SEPTEMBER 2, 2022, at 2:00 p.m. 

Members of the public may view the prehearing conference in person at either of the Commission’s offices or can access the hearing at the time noticed herein via the Commission’s live stream link on its website at https://puc.nv.gov. 

The purpose of the prehearing conference is to formulate and simplify issues involved in this proceeding and set a hearing and procedural schedule. At the prehearing conference, the Commission may take any action authorized by NAC 703.655. 

The Commission is not responsible for providing clerical or administrative assistance or materials to parties during Commission proceedings. If such assistance is necessary, parties must make other arrangements for this type of assistance. 

The Joint Application is available for public viewing at the Commission’s website: https://puc. nv.gov; and at the offices of the Commission: 1150 East William Street, Carson City, Nevada 89701 and 9075 West Diablo Drive, Suite 250, Las Vegas, Nevada 89148. 

A person must request in writing to be placed on the service list for this proceeding to receive any further notices in this matter. 

By the Commission, 

/s/ 

TRISHA OSBORNE, 

Assistant Commission Secretary 

Dated: Carson City, Nevada 

08/05/22 

(SEAL) 

Pub Date: August 17, 2022 Ad # 26857

Comments

Use the comment form below to begin a discussion about this content.

Sign in to comment