Minden road work

The following information was provided by the Town of Minden for road work May 31-June 25. Hours are 7 a.m.-7 p.m. with no weekends anticipated for the 45-calendar-day life of the project. Information, Tim Russell, 883-1600.

May 31- June 2 No work

June 3-4 Crack repair and lowering utilities on Wisteria Drive and Lantana Drive (at Lucerne).

June 7-9 Remove and replace base and pavement on Wisteria (Lilac to Lucerne)

June 10 Pave Wisteria, Camellia, and Lantana (at Lucerne).

June 11 Raise utilities and clean up Wisteria, Camellia, and Lantana.

June 14-18 Remove and replace base and pavement on Lantana (near Bougainvillea)

June 21-June 25 Raise utilities and clean-up